The World Heritage Committee,
1. Having examined Document WHC-09/33.COM/7B,
2. Recalling Decision 31 COM 7B.125, adopted at its 31st session (Christchurch, 2007
3. Encourages the adoption, and strict enforcement of the new law on monumental heritage, the Integrated Revitalization Plan and the implementation of the related actions proposed, and the adoption and full implementation of the Risk management plan for the Zona Colonial;
4. Requests the State Party to:
a) Submit to the World Heritage Centre, as soon as possible, the complete technical documentation of the Sans Souci project to be undertaken in the South Area, in conformity with Paragraph 172 of the Operational Guidelines,
b) Withhold any approval of the development until the World Heritage Committee has had the opportunity to fully review the project,
c) Invite a joint World Heritage Centre / ICOMOS reactive monitoring mission to the property to consider its overall state of conservation and particularly the possible impact of the Sans Souci project on the Outstanding Universal Value and integrity of the property and to review the proposal for the delineation and protection of the buffer zone ;
5. Also requests the State Party to submit to the World Heritage Centre, by 1 February 2010, a detailed report on the state of conservation of the property and on the implementation of the above recommendations, for examination by the World Heritage Committee at its 34th session in 2010.