Take advantage of the search to browse through the World Heritage Centre information.

i
ii
iii
iv
v
vi
vii
viii
ix
x

Ħal Saflieni Hypogeum

Malta
Factors affecting the property in 1990*
  • Management activities
  • Micro-organisms
  • Radiation/light
  • Relative humidity
  • Solid waste
  • Temperature
  • Water (rain/water table)
UNESCO Extra-Budgetary Funds until 1990

The special account opened to finance the campaign enabled two experts to be dispatched in 1990 to examine the ventilation system ($8,360)

International Assistance: requests for the property until 1990
Requests approved: 2 (from 1981-1988)
Total amount approved : 11,500 USD
Missions to the property until 1990**

1979: expert mission on climatology and hydrology;  1980: expert mission in hydrology  ;  1990: expert mission to examine the ventilation system 

 

Conservation issues presented to the World Heritage Committee in 1990

This site, placed on the World Heritage List in 1980 under criterion (iii), is one of the monuments concerned by the safeguarding campaign launched on behalf of Malta.

In 1979, with financing provided by the Fund ($2,300), an expert was dispatched to study the problems of climatology and hydrology and to advise the competent authorities regarding the equipment needed to remedy them.

A request was made to the World Heritage Fund in 1981 for the purpose of securing air-conditioning equipment ($3,570).

When the Working Croup established under the International Campaign visited the Hypogeum in April 1983, they noted the problems caused by the high humidity, including the growth of algae on the walls which were damaging the wall paintings, and recommended that the services of experts in hydrology and in ventilation be provided, that modifications be made to the lighting system, and that the buildings overhanging the Hypogeum be demolished and a new entrance built.

The authorities have been monitoring the temperature and level of humidity in the Hypogeum over a period of 3 1/2 years with equipment provided by Unesco. A $2,700 allocation from the Fund served to send an expert in hydrology who visited the Hypogeum in December 1988 to help determine the origin of the water infiltrating the Hypogeum; his preliminary conclusions were that the main source was groundwater coming from the supply water system and, in particular, used water. Further tests and analyses are being carried out. The lighting system has been modified, with the result that the algae are not developing further. In addition, the special account opened to finance the campaign enabled two experts to be dispatched in 1990 to examine the ventilation system ($8,360); _their report can be consulted in the Secretariat. French experts who worked at Lascaux visited the Hypogeum in June 1990 and advised on the question of ventilation, visitor control and on the new entrance for which architectural plans have already been prepared. The buildings overhanging the Hypogeum have already been demolished and it is now urgent to construct the new entrance to provide adequate protection for the monument.

Summary of the interventions
This report was not discussed during the World Heritage Committee session.
Decisions adopted by the Committee in 1990

No draft Decision

Report year: 1990
Malta
Date of Inscription: 1980
Category: Cultural
Criteria: (iii)
Documents examined by the Committee
arrow_circle_right 14COM (1990)
Exports

* : The threats indicated are listed in alphabetical order; their order does not constitute a classification according to the importance of their impact on the property.
Furthermore, they are presented irrespective of the type of threat faced by the property, i.e. with specific and proven imminent danger (“ascertained danger”) or with threats which could have deleterious effects on the property’s Outstanding Universal Value (“potential danger”).

** : All mission reports are not always available electronically.


top