XII.101 In response to an ICOMOS mission to the site in April 2001 to assess the impact of a road project foreseen in the vicinity of the Tiefurt Castle and its Park at Weimar, at which the road proposal (Variant 1) was identified as having the least impact on the site, the progress report provided by the Ministry of Science of the State of Thuringia confirmed that the decision to proceed with the road proposal (Variant 1) had been reached.
XII.102 The Bureau thanked the German authorities for the progress report and congratulated them on the choice of the road proposal (Variant 1) which will have the least impact on the site. It requested the authorities to keep the Centre informed of the progress of this project.