The World Heritage Committee,
- Having examined Document WHC/19/43.COM/7B,
- Recalling Decision 41 COM 7B.92, adopted at its 41st session (Krakow, 2017),
- Requests the State Party, as a matter of high priority, to submit the completed Conservation and Management Plan of the property to the World Heritage Centre, for review by the Advisory Bodies prior to its adoption and implementation;
- Also requests the State Party to submit to the World Heritage Centre the detailed plans and technical documents concerning the physical interventions with potential impacts on the Outstanding Universal Value (OUV) of the property, which are included or not included in the draft Conservation and Management Plan prior to its finalization or implementation, for review by the Advisory Bodies, ensuring that it includes an assessment of the property’s vulnerability to disasters such as earthquakes or fires, and a systematic strategy for disaster risk reduction;
- Further requests the State Party to submit to the World Heritage Centre, for review by the Advisory Bodies, and before any further implementation of works is undertaken:
- Information on the development of the spatial structure for the motorized and pedestrian roadways for visitors to the property,
- Detailed information on further planned reorganization of the sewage system within the property and its buffer zone;
- Requests furthermore the State Party to submit:
- Details of any planned anti-earthquake consolidation projects to the World Heritage Centre, for review by the Advisory Bodies, before their implementation,
- Architectural and photographic details of the anti-earthquake consolidation that is implemented to the Ali Qapu Pavilion and other built structures in the property;
- Reminds the State Party of the requirement to submit to the World Heritage Centre, for review by the Advisory Bodies, detailed information, including Heritage Impact Assessments (HIAs), for any large tourism and/or development projects, which have a potential to impact the OUV of the property, in accordance with Paragraph 172 of the Operational Guidelines before works commence or any irreversible decision is made;
- Finally requests the State Party to submit to the World Heritage Centre, by 1 December 2020, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Committee at its 45th session in 2021.