The World Heritage Committee,
- Having examined Document WHC/19/43.COM/7B,
- Recalling Decision 41 COM 7B.84, adopted at its 41st session (Krakow, 2017),
- Notes that the Management Plan is under finalization by the State Party and encourages its submission together with a timetable for its implementation, ensuring that there is no gap between the operation of the previous plan and forthcoming one, as soon as possible to the World Heritage Centre for consideration by the Advisory Bodies;
- Also notes that the proposed special account for conservation has not been established yet, and also encourages the State Party to provide an update on its status once further information is available;
- Requests the State Party to provide a Heritage Impact Assessment (HIA) of the pedestrian footbridge, including a section on the potential impact of the bridge on the Outstanding Universal Value (OUV) of the property, for examination by the Advisory Bodies;
- Acknowledges that the first phase of restoration works has been carried out on the basis of assessments and studies, and also requests the State Party to transmit detailed information on intervention projects, and documentation on the planned additional phases to the World Heritage Centre, prior to the commencement of works and in accordance with Paragraph 172 of the Operational Guidelines, for consideration by the Advisory Bodies;
- Reiterates again its recommendation to the State Party to adopt an integrated approach focusing on the Historic Urban Landscape (HUL) as an additional tool for the sustainable management of the property;
- Further requests the State Party to submit to the World Heritage Centre, by 1 December 2020, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Committee at its 45th session in 2021.