The World Heritage Committee,
1. Having examined Document WHC-13/37.COM/7B.Add,
2. Recalling Decision 35 COM 7B.134, adopted at its 35th session (UNESCO, 2011),
3. Acknowledges the efforts made by the State Party in the implementation of the recommendations made by the 2010 reactive monitoring mission and encourages it to continue with these efforts, in particular regarding the establishment of a fully functional and resourced management system for the property;
4. Takes note of large scale projects being implemented and requests the State Party to:
a) Consider the development of alternative plans for the High Capacity Segregated Corridor, responsive to studies of transportation systems, and develop the adequate heritage impact assessments in the sections that could potentially impact the World Heritage property,
b) Submit to the World Heritage Centre the final design, technical specifications and precise location of the route, in relation to the inscribed property, for the Cable Car Project, including relevant heritage and visual impact assessments, for review by the Advisory Bodies prior to making any commitment to its implementation by 30 October 2014;
5. Also requests the State Party to submit three printed and electronic copies of the finalised Master Plan for review by the World Heritage Centre and the Advisory Bodies;
6. Further requests the State Party to submit to the World Heritage Centre, by 1 February 2015 , an updated report on the state of conservation of the property and the implementation of the abovementioned requests, for examination by the World Heritage Committee at its 39th session in 2015.