The World Heritage Committee,
1. Having examined Document WHC-09/33.COM/7B,
2. Recalling Decision 32 COM 7B.116, adopted at its 32nd session (Quebec City, 2008),
3. Notes the results of the November 2008 joint World Heritage Centre / ICOMOS reactive monitoring mission and the good overall state of conservation and management of the property;
4. Expresses its satisfaction that the Dyson Academy Project has officially been withdrawn;
5. Strongly recommends that the State Party submit to the World Heritage Centre and ICOMOS, for review, a revised plan showing that all necessary social facilities have been included in the first Phase of the Bath Western Riverside project;
6. Urges the State Party to submit to the World Heritage Centre and ICOMOS, for review, a time-bound revised plan for the second and third phases of the Bath Western Riverside project, including revised density and volume of the ensemble, so as not to impact on the Outstanding Universal Value of the property, its integrity and on important views to and from the property;
7. Also recommends that the State Party enhance the protection of the surrounding landscape of the property to prevent any future developments which could have adverse and cumulative impact on the Outstanding Universal Value of the property;
8. Invites the State Party to embark on a reinforced, integrated and homogenous interpretation for all the attributes bearing the Outstanding Universal Value of the property;
9. Requests the State Party to submit to the World Heritage Centre, for information and by 1 February 2011, the draft of the revised management plan, including the integrated and comprehensive Tourism management plan, the integrated Public Realm and Movement Strategy, respecting both the authenticity and integrity of the property, and the integrated Traffic Control Plan, before its final adoption.