The World Heritage Committee,
- Having examined Document WHC/17/41.COM/7B,
- Recalling Decision 39 COM 7B.76, adopted at its 39th session (Bonn, 2015),
- Noting that the final plans concerning the proposed new development at Residential Area Dr. Franz-Rehrl Platz (Residential Buildings City Life Rehrlplatz) were submitted to the World Heritage Centre, requests however the State Party to further revise these plans before approval of the project, as long as the recommendations of the 2013 ICOMOS Advisory mission remain unfulfilled;
- Also noting that a modified version of the development project at Schwarzstrasse 45 / Ernest-Thunstr. 2 has already been built, regrets that the State Party did not provide more detailed information with regard to the implementation of the recommendations of the 2013 mission;
- Further noting that the construction work of a modified version of the Nelböck Viaduct Rainerstrasse / Bahnhofsvorplatz project has already started, also requests the State Party to provide more information on this project as well as details on the modified project of the Public Indoor Swimming Pool Paracelsusbad, with regard to the implementation of the recommendations of the 2013 mission, and to keep the World Heritage Centre informed on any future developments regarding the halted Residential Building Priesterhausgarten;
- Reiterates its concern about the apparent lack of adequate legislative and planning mechanisms to protect the property from the various proposed urban and infrastructure developments and further requests the State Party to:
- Develop a comprehensive urban land use plan, which includes provisions for protection mechanisms and regulatory measures to ensure the adequate protection and control of the property and its landscape setting,
- Strengthen legal mechanisms for the protection of monuments in their setting,
- Carry out Heritage Impact Assessments (HIAs) for projects, which may threaten the Outstanding Universal Value (OUV) for the property, in conformity with the ICOMOS Guidelines on HIAs for World Heritage cultural properties, such as the development project at Schwarzstrasse 45 / Ernest-Thunstr. 2, the project at Nelböck Viaduct Rainerstraße / Bahnhofsvorplatz, and the Public Indoor Swimming Pool Paracelsusbad project;
- Notes that the legal process to harmonize the boundary of the property with the Protection zone I has been completed and strongly encourages the State Party to complete the revision of the Management Plan, including provisions to ensure adequate protection and conservation of all attributes, which convey the OUV of the property, and its setting and submit it to the World Heritage Centre for review by the Advisory Bodies;
- Urges the State Party to implement all the recommendations of the 2013 ICOMOS Advisory mission;
- Requests furthermore the State Party to submit to the World Heritage Centre, by 1 December 2018, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Committee at its 43rd session in 2019.