The World Heritage Committee,
- Having examined Document WHC/16/40.COM/7B.Add,
- Recalling Decision 39 COM 7B.30, adopted at its 39th session (Bonn, 2015),
- Regrets that the State Party did not submit a report on the state of conservation of the property, as requested by the Committee;
- Takes note of the Environmental Impact Assessments (EIAs) for exploration and production phases of the geothermal project in the Roseau Valley submitted by the State Party to the World Heritage Centre;
- Noting that the abovementioned EIAs do not include an assessment of potential impacts of the project on the Outstanding Universal Value (OUV) of the property, reiterates its request to the State Party to prepare such an EIA, in line with IUCN’s World Heritage Advice Note on Environmental Assessment, and urges again the State Party to suspend the geothermal project until the above mentioned EIA has been submitted to the World Heritage Centre, and reviewed by IUCN;
- Also reiterates its request to the State Party to invite a joint World Heritage Centre/IUCN Reactive Monitoring mission to the property, to assess the impacts of existing geothermal infrastructure, and the current status of the geothermal project in the Roseau Valley and its potential impacts on the OUV of the property;
- Requests the State Party to submit to the World Heritage Centre, by 1 February 2017, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Committee at its 41st session in 2017.