Decision 44 COM 7B.60
Cornwall and West Devon Mining Landscape (United Kingdom of Great Britain and Northern Ireland) (C 1215)

The World Heritage Committee,

  1. Having examined Document WHC/21/44.COM/7B,
  2. Recalling Decision 43 COM 7B.93, adopted at its 43rd session (Baku, 2019),
  3. Welcomes the significant progress of the State Party in:
    1. applying the Supplementary Planning Document, Planning Performance Agreements and neighbourhood development plans to protect the Outstanding Universal Value (OUV) of the property,
    2. implementing the recommendations of the 2015 joint ICOMOS/ICCROM Reactive Monitoring mission,
    3. updating the Management Plan, in order to protect the OUV of the property,
    4. establishing revised arrangements and adjusted timeframes for consultation with the World Heritage Centre and ICOMOS regarding specific projects, including the proposed North Quay Phase 2 projects;
  4. Encourages the State Party to ensure that the advice of Historic England and the World Heritage Site Planning Officer continue to inform statutory decision making, so as to ensure that there are no adverse impacts on the property’s OUV;
  5. Requests the State Party to implement fully the recommendations of ICOMOS related to the North Quay Phase 2 projects in order to avoid the identified potential negative impacts of the project application to the OUV of the property;
  6. Reiterates its previous request to the State Party to submit further information about proposals for the South Crofty Mine; in particular details of the boundary treatment and planning;
  7. Notes its previous request that the State Party continue to ensure that, in line with Paragraph 172 of the Operational Guidelines, details for significant changes to statutory documents and any new planning applications which may affect the OUV of the property are appropriately selected and are submitted to the World Heritage Centre, for review by the Advisory Bodies, before final decisions are taken;
  8. Finally requests the State Party to submit to the World Heritage Centre, by 1 December 2022, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Committee at its 46th session.
Documents
WHC/21/44.COM/18
Decisions adopted at the 44th extended session of the World Heritage Committee
Context of Decision
WHC-21/44.COM/7B