1.         Ephesus (Türkiye) (C 1018rev)

Year of inscription on the World Heritage List  2015

Criteria  (iii)(iv)(vi)

Year(s) of inscription on the List of World Heritage in Danger  N/A

Previous Committee Decisions  see page https://whc.unesco.org/en/list/1018/documents/

International Assistance

Requests approved: 0
Total amount approved: USD 0
For details, see page https://whc.unesco.org/en/list/1018/assistance/

UNESCO Extra-budgetary Funds

N/A

Previous monitoring missions

N/A

Factors affecting the property identified in previous reports

Illustrative material  see page https://whc.unesco.org/en/list/1018/

Conservation issues presented to the World Heritage Committee in 2019

On 4 December 2018, the State Party submitted a state of conservation report, which is available at http://whc.unesco.org/en/list/1018/documents/ and addresses the recommendations of the World Heritage Committee as follows:

Analysis and Conclusions of the World Heritage Centre, ICOMOS and ICCROM

The detailed information and confirmation of the legislative protection for the buffer zone of the property are welcomed. However, it appears that some parts of the buffer zone have no protective designation – a moderately large area to the south of the property on the western side, a small area to the southeast of the property, and a small area to the east of the property.

Information provided regarding the revision process for the Management Plan is noted. It is important that this revision include research and conservation programmes for the overall property, with a provision for findings to be integrated into future management, education and interpretation, as well as the extension of the monitoring system to relate to the inventory/database of the property. It is recommended that the Committee request the State Party to submit the draft revised version of the Management Plan to the World Heritage Centre, for review by the Advisory Bodies, as soon as it becomes available.

Information about the disapproval of the cable car project by the Regional Conservation Council is also noted. It is recommended that the Committee request the State Party to keep the World Heritage Centre informed on any developments regarding this project. To this aim, it is recommended that the Committee request the State Party to submit to the World Heritage Centre, for review by the Advisory Bodies the details of any newly submitted project proposal and the results of the HIA, before any irrevocable decisions are taken concerning this project.

In addition, while the State Party advises that no major restoration, alteration and/or new construction which may affect Outstanding Universal Value of the property is intended within the World Heritage property or buffer zone, it notes that it intends to undertake the modernization and rehabilitation of both entrances gates. While this information is to be noted, pending the sending by the State Party of detailed information on these projects including an HIA. It is therefore requested State Party to submit the details of the projects and the results of the HIA, before any irrevocable decisions are taken concerning these projects.

Decision Adopted: 43 COM 7B.91

The World Heritage Committee,

  1. Having examined Document WHC/19/43.COM/7B,
  2. Recalling Decision 41 COM 7B.51, adopted at its 41st session (Krakow, 2017),
  3. Welcomes the information related to the approval of the legislative protection for the buffer zone of the property;
  4. Requests the State Party to submit the draft revised Management Plan to the World Heritage Centre, for review by the Advisory Bodies, as soon as it becomes available;
  5. Also requests the State Party to include within the revised Management Plan a summary statement about the effectiveness of the set of measures to achieve integrated protection for the property; in particular, to provide a clear explanation of the effectiveness of particular measures, especially the Interaction Transition Zone and Forestry Act, to protect the Outstanding Universal Value (OUV) of the property;
  6. Further requests the State Party to clarify, within the revised Management Plan, the protective designation of the entire buffer zone, in particular those areas, which currently appear to have no protective designation;
  7. Takes note of the information about the disapproval of the cable car project by the Regional Conservation Council and requests furthermore the State Party to keep the World Heritage Centre informed on any developments regarding this project, and submit to the World Heritage Centre, for review by the Advisory Bodies, the details and results of the Heritage Impact Assessment (HIA), including a section on the potential impacts of any newly submitted project proposal on the OUV of the property, before any irrevocable decisions are taken concerning this project;
  8. Requests moreover the State Party to provide all relevant information related to the project that modernizes and rehabilitates the entrances at both gates, including a Heritage Impact Assessment, in conformity with Paragraph 172 of the Operational Guidelines;
  9. Finally requests the State Party to submit to the World Heritage Centre, by 1 December 2020, an updated report on the state of conservation of the property and the implementation of the above, for examination by the World Heritage Centre and the Advisory Bodies.