jump to the content

State of Conservation (SOC)

Madriu-Perafita-Claror Valley (2008)

UNESCO Extra-Budgetary Funds
International Assistance granted to the property

Requests Approved: 0
Total Amount Ap proved: 0USD

Missions**
Factors* affecting the property identified in previous reports

a) Legal protection for buffer zone;

b) Completion of management plan and inventory.

Corrective Measures
Current conservation issues

Current conservation issues

In its report submitted on 31st January 2008, the State Party reported progress on legal protection, and the management plan.

a) Legal protection

The State Party reported that the Law to protect the property as a cultural landscape, the details of which were given in the report to the 30th session of the World Heritage Committee (Vilnius, 2006), were finally adopted and entered into force on 26 July 2006.

b) Management plan progress

The State Party reported that there have been difficulties in getting agreement to an overall approach for the management plan from all the four communes within the inscribed property. At the time of inscription, the development of a management plan was well advanced with the involvement of all the communes. However since that time, two of the communes, Encamp and Escaldes-Engordany, have instigated legal proceedings against the Government stating that the inscription of the property and measures to protect it as a cultural landscape have challenged their competences. This matter was considered by Constitutional Tribunal and the challenge not upheld. However progress with the management plan was halted during the time taken to resolve these issues and this has set back the overall timescale.

Conclusion
Decision
  • Adopted

  • Draft Decision

32COM7B.80
Link to the decision

The World Heritage Committee,

1. Having examined Document WHC-08/32.COM/7B.Add,

2. Recalling Decision 30 COM 7B.80, adopted at its 30th session (Vilnius, 2006),

3. Notes that the Law to protect the property as a cultural landscape entered into force in July 2006;

4. Also notes delays in finalizing the management plan while awaiting the outcome of legal challenges;

5. Requests the State Party to submit to the World Heritage Centre, by 1 February 2010, a progress report on the implementation of the management plan, for examination by the World Heritage Committee at its 34th session in 2010.

Draft Decision: 32 COM 7B.80

The World Heritage Committee,

1. Having examined Document WHC-08/32.COM/7B.Add,

2. Recalling Decision 30 COM 7B.80, adopted at its 30th session (Vilnius, 2006),

3. Notes that the Law to protect the property as a cultural landscape entered into force in July 2006;

4. Also notes delays in finalizing the management plan while awaiting the outcome of legal challenges;

5. Requests the State Party to submit to the World Heritage Centre, by 1 February 2010, a progress report on the implementation of the management plan, for examination by the World Heritage Committee at its 34th session in 2010.

 

Madriu-Perafita-Claror Valley
State Party:
Andorra
Date of Inscription: 2004
Nomination records (Year): 2003, 2006
Category: Cultural
Criteria: (v)
Exports
Word File
SOC Reports (year)
2012
2010
2008
2006
2005
Threats*
  • Legal framework
  • Management systems/ management plan
  • Other Threats:


* : The threats indicated are listed in alphabetical order; their order does not constitute a classification according to the importance of their impact on the property.
Furthermore, they are presented irrespective of the type of threat faced by the property, i.e. with specific and proven imminent danger (“ascertained danger”) or with threats which could have deleterious effects on the property’s Outstanding Universal Value (“potential danger”).

** : All mission reports are not always available electronically.